Construction Change Directive: A Subcontractor's Guide

What a construction change directive is, how it differs from a change order, and how subcontractors should document and price directed work to get paid.

Construction Change Directive: A Subcontractor’s Guide

Owner signs a construction change directive

A construction change directive (CCD) is a written order from the owner, prepared by the architect, telling the contractor to proceed with changed work before anyone has agreed on its price or schedule impact (AIA Contract Documents). For a subcontractor, that means you may be told to start work with the money still undecided. What protects you is how fast and how well you document the work.

Won2build
won2build.com
Keep Change Work Visible
Won2Build helps subcontractors track labor and manage change orders, with field and office data synchronized across its construction software suite.
Explore the software suite

TL;DR

  • A CCD directs changed work now and settles cost and time later. A change order records an agreement already reached.
  • Under AIA A201, the owner can issue a CCD without the contractor’s signature, and the contractor is generally expected to proceed.
  • Proceeding does not mean giving up your claim. Track labor, materials and schedule impacts from the first hour.
  • Notice deadlines come from your contract and flow down from the prime agreement. Read them before the first directive arrives, not after.
  • Final price and time adjustments are normally folded into a later change order once the parties agree.

Table of Contents

What a construction change directive is

The CCD exists because jobs do not wait for negotiations. When the owner needs a change made and a delay would hurt the project, the architect prepares a directive and the owner signs it. AIA’s G714-2017 form defines the CCD as the mechanism for changing the work when the owner and contractor have not agreed on the adjustment to the contract sum or contract time (AIA Contract Documents, G714-2017 summary).

Under the A201 General Conditions, the owner can issue a CCD without the contractor’s signature, and the contractor is generally required to proceed with the directed work so the project is not delayed (AIA Contract Documents). Once the contractor receives a completed directive, it must proceed with the described change (G714-2017 summary).

Two things follow for a subcontractor:

  1. The directive usually reaches you through your general contractor. The terms of your subcontract decide how much of the prime contract’s directive process binds you.
  2. You are being told to perform, not told what you will be paid. Those are separate questions, and keeping them separate is the core skill.

Public owners use their own versions. The Engineers Joint Contract Documents Committee form is often called a work change directive, and a USDA Rural Development guide to that form makes the same point: a directive is not itself a change order, it authorizes work that may later be included in one (USDA Rural Development). The name changes. The logic does not.

Change directive vs. change order

This is the question most readers actually have. The difference is timing and agreement.

AIA’s A201 provisions distinguish the two this way: a change order records agreement among the owner, contractor and architect on the changed work and any adjustment to contract sum and time, while a CCD is issued before that agreement exists (EJCDC comparison of standard form contracts).

Change order Construction change directive
Agreement on price and time Already reached Not yet reached
Who signs (AIA A201) Owner, contractor and architect Owner and architect
Contractor’s position Agreed to the terms Must proceed, then advise whether it agrees with the proposed pricing method
Typical use Changes with a defined scope and time to price Urgent or undefined changes that cannot wait
What happens next Contract sum and time are adjusted Adjustments are settled later, usually by a change order

The signature sources are the same A201 comparison: the architect prepares the CCD, the owner and architect sign it, and the contractor must proceed and tell the architect whether it agrees with the proposed method of adjustment (EJCDC comparison).

A useful way to hold it: a change order is a deal, and a directive is an instruction that promises a deal will follow. If your price is not yet agreed, you do not have a change order, whatever the foreman calls the paperwork. Our guide on getting paid for unsigned change orders covers what to do when work is moving without a signed document.

When owners issue a CCD

Directives show up when speed matters more than a settled price. AIA describes the typical triggers as urgent work that cannot wait for negotiations, such as unforeseen site conditions, safety emergencies or code compliance changes (AIA Contract Documents). Minnesota State’s change order guidance adds a practical one: directives are used when there is no definitive scope of work or not enough time to process a proposal into a formal change order (Minnesota State).

For commercial subs, the common field versions look like this:

  • A concealed condition opens up behind a wall and the design team needs a revised detail installed this week.
  • A code official requires a change and the inspection sequence cannot slip.
  • The owner wants an area accelerated or resequenced and will sort out the cost afterward.

In each case the pressure is on you to start. The leverage you have is in the record you build.

What a good directive contains

A vague directive is a risk to you because it leaves scope open to argument later. A form from a public owner shows what a complete one carries. It identifies the project and parties, the directive number and dates, describes the changed work and its purpose, lists attachments, explains why the work must proceed before agreement, states preliminary price and time impacts, identifies the pricing method, and shows the engineer’s recommendation and the owner’s authorization (Puerto Rico work change directive form). The same form gives the proposed basis for estimating the change, which may be lump sum, unit price, cost of the work or another basis.

Before you mobilize, check the directive against this list:

  • Scope: Can you tell exactly which drawings, areas and quantities are included?
  • Reason: Does it say why the work cannot wait?
  • Pricing method: Lump sum, unit price, or time and materials?
  • Preliminary cost and time: Is there a placeholder, even a rough one?
  • Authorization: Is it signed by the people your contract requires?

If something is missing, ask in writing for clarification and keep working on the part that is clear. Asking is not refusing.

What to do in the first 24 hours

The most useful advice on this comes from practicing construction attorneys. Their guidance for subcontractors is to photograph existing conditions and progress right away, track labor and materials under dedicated cost codes or tickets, and give written notice of impacts before the end of the next business day. Any expected schedule, productivity or disruption problems should go to the project manager as well (Modern Contractor Solutions, presented to the International Association of Defense Counsel).

Turned into a routine:

  1. Log the directive. Record the number, date, who delivered it and how.
  2. Photograph before you touch anything. Existing conditions and the state of related work.
  3. Open a dedicated cost code. Nothing about the directed work should be buried in base-contract labor.
  4. Send written notice. Acknowledge the directive, state that impacts to cost and schedule are expected, and say you are proceeding.
  5. Tell the PM about knock-on effects. Resequencing, stacked trades, delayed deliveries.
  6. Tag every labor ticket with the directive number, daily.

The daily ticket step is where most subs lose money. A foreman who writes “extra work, 6 hrs” on a Friday cannot rebuild what happened on Tuesday. Our four-step daily T&M ticket checklist and the same-day field documentation checklist walk through what each ticket should capture. The same-hour notice approach helps when the clock on your notice requirement is short.

Keep four questions separate

The same attorneys warn against merging four questions into one conversation: whether there is a directive, what the scope is, what the impact is and who pays. Merging them leaves the subcontractor carrying the exposure (Modern Contractor Solutions). A project manager who says “just get it done, we’ll figure out money later” is mixing all four. A short email that restates each one separately fixes that.

Four questions kept separate in a CCD

Pricing the directed work

Price and time adjustments are determined through the contract’s pricing methods, or by the architect based on documented costs. Once the parties agree, they typically execute a change order to incorporate the adjustments (AIA Contract Documents). Minnesota State describes the same sequence on public work: after the directed work, the contractor submits labor and material costs and any time adjustments for incorporation into a later change order (Minnesota State).

So your documentation is the price. If the architect determines the cost, the architect works from what you can prove.

A complete change proposal covers more than visible labor and materials. Supervision, equipment, rework of adjacent finished work, remobilization and lost productivity all belong in the count when they are real. The discipline applies in every trade; even how roofing subcontractors define their roles shows how many separate pieces of work sit inside a single scope. Our guide to change order pricing with daily T&M tickets shows how to build the number from the field record.

If you disagree with the architect’s number

Under AIA A201, a contractor that disagrees with the architect’s determination of a CCD’s cost adjustment may bill the determined amounts while pursuing a claim for the final figure (imHORA). That keeps cash moving without conceding the dispute. Your subcontract may route this through your general contractor, so confirm how.

Payment timing varies by owner and state

Some public-work statutes put a clock on payment. In Washington, within 30 days after satisfactory completion of additional work and receipt of a request for a change order, the owner, state or municipality must issue an order for the undisputed amount, and interest accrues if it does not (RCW 39.04.360). That is one state’s rule on public work, not a national one. Check your own state’s prompt payment and public contracting statutes, or ask your attorney.

Notice and contract terms to check before you proceed

The directive itself is rarely where subs get hurt. The hurt comes from missed notice windows. Read these in your subcontract and the prime contract it flows from:

  • Notice deadlines. On federal work under the Changes clause, a claim must be submitted within 30 days of receipt of a written change order or the date of initial notice, whichever applies (American Bar Association). Private contracts set their own periods, often shorter.
  • Approval before extra work. Some owners require approval first. New York DOT projects, for example, call for a contract change order to be approved before extra work is performed (NYSDOT). A directive is how that rule is handled when work cannot wait, so know which instrument your owner uses.
  • Separate claims for ripple effects. Effects of a CCD beyond the changed work, such as disruption, typically need their own claim notice under provisions like A201 Article 15 (imHORA). Do not assume the directive notice covers them.
  • Flow-down clauses. Your general contractor’s obligations to the owner often pass to you, along with their deadlines, and the general contractor’s own internal deadline to you can be earlier.

One attorney commentary in the American Bar Association’s construction series notes that enforcing CCD provisions against contractors seems at odds with the traditional common law expectation of mutual consideration, yet courts consistently uphold these contractual rights (ABA, Construction 101). The practical lesson is that arguing the clause is unfair rarely works. Following it does.

The American Subcontractors Association’s change order white paper quotes Ron Churchey’s view that the more detailed the original contract is on scope and performance, the easier it is to establish entitlement for changes and avoid disputes (ASA). For you, that means your bid scope, inclusions and exclusions are your first line of defense when a directive arrives. If you want that groundwork tighter, see why subcontractors overbid and underbid.

After the work: closing the loop

A directive that never becomes a change order is unpaid work. Once the directed work is done:

  1. Submit your cost backup, daily tickets and time impact in the format the contract requires.
  2. Track the proposal until the change order is executed and added to the contract sum.
  3. Keep a running log so nothing sits unresolved at closeout.

Backlog is where margin quietly disappears. Our posts on change order log management, 48-hour change order management and change order backlog cover the habits that keep approved and pending changes visible. If you need a starting document, the change order template with six required fields is editable.

Our view: the directive is won or lost in the field record

We build software for subcontractors, and we hear the same story about directives again and again. The owner’s instruction is clear. The subcontractor’s proof is not. Hours get written on paper tickets at the end of the week, the office re-keys them, and by the time a price is requested nobody can say which crew did what on which day.

That is why we designed Won2Build Hub as one suite with a single login. Time Budge is built to capture labor against a job and cost code in the field. CO Hub is built to manage change orders and T&M tickets. Bid Track keeps your original estimate and scope in view, and Takeoff helps quantify plans. Because the apps share one sign-on, the field entry is meant to carry into the office without double entry.

Our position is simple: a subcontractor should be able to answer “what did this directive cost us?” with a record, not a recollection. Do that and the pricing conversation becomes a matter of arithmetic instead of argument.

Jen Reese

Put the paper trail on rails

If directives reach your crews faster than your paperwork can keep up, a connected system helps. Won2Build Hub gives commercial subcontractors labor tracking, change order and T&M ticket management, bid tracking and takeoff under one login.

Won2build

Published pricing is on the pricing page: Time Budge is $199 per month per company, CO Hub is $59 per month per company, and the active field worker fee is $2 per month per active field worker. Takeoff and the Hub are listed at $0 per month. You can also see the full product lineup.

FAQ

What does CCD mean in construction?

CCD stands for construction change directive. It is a written order, prepared by the architect and signed by the owner under AIA documents, that directs a change in the work before the parties have agreed on its cost or time effect. The contractor is generally required to proceed.

What is the difference between a change directive and a change order?

A change order records an agreement on the changed work and any adjustment to price and time. A change directive is issued before that agreement exists, so work can start while the numbers are still open. Directive adjustments are usually settled later by a change order.

Do I have to proceed if I disagree with a CCD?

Under AIA A201, the contractor is generally required to proceed and then tell the architect whether it agrees with the proposed pricing method. Disagreement goes into written notice and a claim, not a work stoppage. Have your attorney review your subcontract’s dispute and flow-down terms before refusing any directed work.

Who pays for work done under a CCD?

The owner pays for the changed work, in the amount determined through the contract’s pricing methods or by the architect from documented costs. If you disagree with the architect’s figure, A201 lets you bill the determined amount while pursuing a claim for the rest. Your records decide how strong that claim is.

What should a subcontractor document under a directive?

Photograph existing conditions, track labor and materials under a dedicated cost code or daily ticket, and send written notice of impacts quickly. Record any schedule, productivity or disruption effects separately, since they typically need their own claim notice.

Sources